Work commenced on the Clubhouse Refresh project this week, with painters and an electrician working on the Great Room. They will move to other areas of the Clubhouse next week. The acoustic panel installers are scheduled to begin installation Sept. 26, with completion ranging from five to eight days, depending on the size of the installation crew. Flooring is currently scheduled to be installed between Oct. 6-13, if all materials are received on-time.